Rooftop solar array at The Print Factory, Enniskillen — six blocks of all-black panels on the pale steel roof of the production building, a B9 Renewables commercial install

Commercial case study · Enniskillen, Co. Fermanagh

Rooftop solar for The Print Factory

A 108-panel, circa 50 kWp daytime-load array on an industrial roof in Enniskillen — designed, grid-approved under G99 and commissioned for a Northern Ireland print works that uses its power when the sun is up.

  • Free survey, fixed written quote
  • Manufacturer warranties registered
  • NICEIC-approved electrical contractors
  • Grid paperwork handled

The project in numbers

panels
108
array size
c. 50 kWp
three-phase inverter
40 kW
grid connection
G99
Full project facts
Segment
Commercial / light industrial
Location
Lackaghboy Industrial Estate, Enniskillen BT74 4RL
Array
108 panels, circa 50 kWp rooftop PV
Inverter
Solis 40 kW three-phase hybrid, grid-tied — no battery
Grid connection
G99 application to NIE Networks at 40 kW
Battery / EV
None in scope
Commissioned
Summer 2026

Daytime load on an industrial roof

The Print Factory is a family print business founded in 1984, producing print, workwear and promotional products from a manufacturing facility in Enniskillen. Its load profile is the classic Northern Ireland commercial one: presses, finishing and building services running through daylight hours.

That is where rooftop solar earns its keep here. With no Smart Export Guarantee in Northern Ireland, the value of a commercial array is almost entirely in the electricity the business uses itself — so generation has to line up with demand, not with an export tariff.

The brief was a fixed-scope commercial install that would satisfy the insurer's pre-install requirements, pass NIE Networks' G99 process and hand over with full electrical certification — without adding battery storage the business did not need for this phase.

Why it mattered to the client

In its own announcement, The Print Factory describes the solar array as part of a wider sustainability programme: printing on demand to cut waste and stockholding, energy-efficient digital and wide-format presses, recycling of paper, card and production waste, FSC-certified papers where specified, and digital workflows that reduce paper use across the business.

The business also frames the investment as resilience — producing its own electricity to protect against rising energy costs while it keeps investing in production technology.

Speaking to Print Business in October 2026, the general manager said the first full month of figures showed the business using less than half the electricity it used to, and called the investment "well worth it".

What we installed

  • 108-panel rooftop PV array on the south slope of the steel portal-frame production building, circa 50 kWp
  • Solis S6-EH3P40K-H 40 kW three-phase inverter (UK G99 model), running grid-tied with no batteries fitted
  • G99 connection application to NIE Networks at 40 kW, handled by us end to end
  • Electrical installation to BS 7671 including Section 712, carried out and certified by the NICEIC-approved electrical contractors we work with; PV verification to BS EN 62446-1
  • Insurer-ready fire safety package — firefighter rapid shutdown, lockable DC isolation, arc-fault detection enabled at commissioning — plus a structural loading assessment of the roof

Not in scope: Battery storage. The inverter is a hybrid chassis, but this install runs without a battery; adding storage later would be a separate G99 variation.

From survey to switch-on

  1. Step 1

    Survey and design

    Roof structure, array layout and the fit against daytime load were checked before a fixed commercial quote was issued.

  2. Step 2

    Insurer and compliance

    A written response to the insurer's pre-install requirements, aligned with the FPA RC62 and RE3 guidance for rooftop PV.

  3. Step 3

    Grid

    G99 application to NIE Networks at 40 kW, submitted and managed on the client's behalf.

  4. Step 4

    Install and commission

    Array and inverter installed and commissioned; handover pack with the electrical installation certificate and PV verification.

  5. Step 5

    Monitoring

    SolisCloud monitoring set up so the business can see generation against its own consumption.

The install

Mounting rails being set out across the bare steel roof of The Print Factory on install day, an installer in a hard hat in the foreground
Install day: mounting rails set out across the steel roof before the panels went on.
All-black solar panels part-laid over the pale steel roof of The Print Factory, wet panels of the neighbouring rows reflecting the sky
Panels going down over the old steel sheeting — all-black 460 W modules, laid row by row.
Close view up the finished rows of all-black solar panels on The Print Factory roof under an overcast sky
The finished rows, edge to edge up the south slope.
Solis 40 kW three-phase inverter wall-mounted on a brick wall inside The Print Factory, with the emergency stop beside it
The Solis 40 kW three-phase inverter, wall-mounted inside beside the roller door.
External DC isolators and the red firefighter emergency switch mounted on the outside wall of The Print Factory
Lockable DC isolation and the firefighter switch at the building entrance.
Three people standing in front of The Print Factory sign at handover of the solar installation
Handover at The Print Factory.

What the client gets

System
108 panels · circa 50 kWp array · 40 kW inverter
Self-consumption
Generation used on site during production hours
First full month
Electricity use more than halved, on the client's own figures
Annual generation
Modelled for the roof; early monitoring under way

The first-month result is The Print Factory's own figure, given to Print Business in October 2026. It covers a single month, and generation falls over winter, so it is not an annual saving. Figures vary with weather, usage, tariff and export settings. Northern Ireland has no Smart Export Guarantee, so the value of a commercial array is mainly avoided import. No payback figure is published for this project.

Press coverage: The Print Factory reaps sunshine rewards, Print Business, .

We were extremely happy with the service provided. John was professional, helpful and efficient throughout.

The Print Factory, from its press release on the installation

Solar in Enniskillen

Fermanagh is the most rural county we cover and the furthest from our Larne base. We installed the 108-panel array at The Print Factory in Enniskillen, and we cover the whole county, including Irvinestown, Lisnaskea, Magheraveely, Kesh and Derrylin.

What we install in Enniskillen

Thinking about solar on a farm shed or industrial roof?

Free survey, fixed written quote, NIE Networks paperwork handled. Serving all six counties from Larne.

  • Free survey
  • Fixed written quote
  • NIE paperwork handled
  • Part of the B9 Energy group, based in Larne
Get my estimate