Commercial case study · Enniskillen, Co. Fermanagh
Rooftop solar for The Print Factory
A 108-panel, circa 50 kWp daytime-load array on an industrial roof in Enniskillen — designed, grid-approved under G99 and commissioned for a Northern Ireland print works that uses its power when the sun is up.

- Free survey, fixed written quote
- Manufacturer warranties registered
- NICEIC-approved electricians
- Grid paperwork handled
The project in numbers
- Segment
- Commercial / light industrial
- Location
- Lackaghboy Industrial Estate, Enniskillen BT74 4RL
- Array
- 108 panels, circa 50 kWp rooftop PV
- Inverter
- Solis 40 kW three-phase hybrid, grid-tied — no battery
- Grid connection
- G99 application to NIE Networks at 40 kW
- Battery / EV
- None in scope
- Commissioned
- Summer 2026
Daytime load on an industrial roof
The Print Factory is a family print business founded in 1984, producing print, workwear and promotional products from a manufacturing facility in Enniskillen. Its load profile is the classic Northern Ireland commercial one: presses, finishing and building services running through daylight hours.
That is where rooftop solar earns its keep here. With no Smart Export Guarantee in Northern Ireland, the value of a commercial array is almost entirely in the electricity the business uses itself — so generation has to line up with demand, not with an export tariff.
The brief was a fixed-scope commercial install that would satisfy the insurer's pre-install requirements, pass NIE Networks' G99 process and hand over with full electrical certification — without adding battery storage the business did not need for this phase.
Why it mattered to the client
In its own announcement, The Print Factory describes the solar array as part of a wider sustainability programme: printing on demand to cut waste and stockholding, energy-efficient digital and wide-format presses, recycling of paper, card and production waste, FSC-certified papers where specified, and digital workflows that reduce paper use across the business.
The business also frames the investment as resilience — producing its own electricity to protect against rising energy costs while it keeps investing in production technology.
What we installed
- 108-panel rooftop PV array on the south slope of the steel portal-frame production building, circa 50 kWp
- Solis S6-EH3P40K-H 40 kW three-phase inverter (UK G99 model), running grid-tied with no batteries fitted
- G99 connection application to NIE Networks at 40 kW, handled by us end to end
- Electrical installation to BS 7671 including Section 712, carried out and certified by the NICEIC-approved electrical contractors we work with; PV verification to BS EN 62446-1
- Insurer-ready fire safety package — firefighter rapid shutdown, lockable DC isolation, arc-fault detection enabled at commissioning — plus a structural loading assessment of the roof
Not in scope: Battery storage. The inverter is a hybrid chassis, but this install runs without a battery; adding storage later would be a separate G99 variation.
From survey to switch-on
- Step 1
Survey and design
Roof structure, array layout and the fit against daytime load were checked before a fixed commercial quote was issued.
- Step 2
Insurer and compliance
A written response to the insurer's pre-install requirements, aligned with the FPA RC62 and RE3 guidance for rooftop PV.
- Step 3
Grid
G99 application to NIE Networks at 40 kW, submitted and managed on the client's behalf.
- Step 4
Install and commission
Array and inverter installed and commissioned; handover pack with the electrical installation certificate and PV verification.
- Step 5
Monitoring
SolisCloud monitoring set up so the business can see generation against its own consumption.
The install




What the client gets
- System
- 108 panels · circa 50 kWp array · 40 kW inverter
- Self-consumption
- Generation used on site during production hours
- Annual generation
- Modelled for the roof; early monitoring under way
Figures vary with weather, usage, tariff and export settings. Northern Ireland has no Smart Export Guarantee, so the value of a commercial array is mainly avoided import. No savings or payback figures are published for this project.
“We were extremely happy with the service provided. John was professional, helpful and efficient throughout.”
Read more about the service
Solar in Enniskillen
Fermanagh is the most rural county we cover and the furthest from our Larne base, so we batch installs here — which keeps mobilisation costs, and therefore your quote, down.